Routes 2A & 7 Intersection Project

The following details all apply to Routes 2A and 7 Intersection:

  • Location - Routes 2A and 7 Intersection
  • Description - Traffic Signals
  • Current phase - Bid
  • Construction date - 2017
  • Total project estimate - $4,383,600
  • Local funding - $0
  • State funding - $876,720
  • Federal funding - $3,506,880
  • Contact - Bryan Osborne
  • Plans available - Yes, please view the Routes 2A and 7 Intersection Project (PDF).

To read more about this project follow the link below to the Vermont Agency of Transportation's website.

Routes 2A & 7 Intersection Project Information

Routes 2A and 7 Intersection Project