From June 2024 to September 2025, Phase I of project construction will be occurring on Blakely Road, West Lakeshore Drive from Prim Road to the Bayside intersection, and East Lakeshore Drive from the Bayside intersection to just beyond South Bay Circle.
Phase III will involve: Extension of the main collection line, and installation of service connections on Goodsell Point is expected to begin in 2027.